
Updated Sep-2026 C_TS422_2601 Free Exam Files Downloaded Instantly
Practice Exams and Training Solutions for Certifications
NEW QUESTION # 37
Which alternative item strategies are available in bills of material (BOMs) in SAP S/4HANA Cloud Private Edition?
Note: There are 2 correct answers to this question.
- A. First in first out (FIFO)
- B. Simultaneous
- C. Manual maintenance
- D. 100% check
Answer: C,D
NEW QUESTION # 38
Which actions does the system perform by default when you save a confirmation for a finished product in repetitive manufacturing?
Note: There are 3 correct answers to this question.
- A. Reduce run schedule quantities.
- B. Update statistics for the Business Information Warehouse.
- C. Create associated capacity requirements.
- D. Post the goods receipt for the finished product.
- E. Post production costs to the planned order.
Answer: A,C,E
NEW QUESTION # 39
What are the key features of using a low level code?
Note: There are 2 correct answers to this question.
- A. To determine the priority of alternative components inside ATP
- B. To determine the use of subitems inside material BOM (bill of material)
- C. To determine how costs are rolled up by product costing
- D. To determine the sequence in which materials are planned in MRP
Answer: C,D
NEW QUESTION # 40
You want to trigger inhouse production of a semifinished material before a sales order for the corresponding finished good is received.Which planning strategy supports the consumption of planned independent requirements by dependent requirements for the semifinished material?
- A. Production by lot size (30)
- B. Planning at assembly level (70)
- C. Planning with final assembly (40)
- D. Assembly processing with production orders (82)
Answer: B
NEW QUESTION # 41
What are some benefits of planning with planned independent requirements for finished materials?
Note: There are 2 correct answers to this question.
- A. Reduced delivery times
- B. Reduced times for final assembly
- C. Option to forecast planning for production resources
- D. Option to use maketoorder production
Answer: A,B
NEW QUESTION # 42
Why would you use phantom assemblies?
Note: There are 3 correct answers to this question.
- A. To make the assignment of components easier
- B. To simplify the structure of bills of material
- C. To reduce the number of material masters
- D. To increase the number of planning levels
- E. To reduce the number of changes required in bills of material
Answer: A,B,E
NEW QUESTION # 43
How can you achieve a feasible production plan in case of capacity constraints?
Note: There are 3 correct answers to this question.
- A. Reduce the planning time interval.
- B. Determine a time period with available capacity on the planning board.
- C. Execute an infinite production planning run for the critical resources.
- D. Increase the capacity supply in a timephased interval.
- E. Form optimum sequences to reduce setup times.
Answer: B,D,E
NEW QUESTION # 44
Which supply chain planning components can you find in SAP S/4HANA?
There are 2 correct answers to this question.
- A. Supply Network Planning
- B. Supply Chain Control Tower
- C. Capacity Requirements Planning
- D. Advanced Planning
Answer: C,D
NEW QUESTION # 45
Which of the following questions do you have to answer before you start creating a bill of material (BOM)?
Note: There are 2 correct answers to this question.
- A. What status does the BOM have?
- B. Is the material type allowed in the BOM?
- C. Which base unit of measure does the material have?
- D. In which storage location is the BOM required?
Answer: A,B
NEW QUESTION # 46
Which of the following elements does MRP take into account during net requirement calculation?
Note: There are 2 correct answers to this question.
- A. Planned orders (firmed)
- B. Planned orders (unfirmed)
- C. Production orders
- D. ATP quantities
Answer: A,C
NEW QUESTION # 47
What generates capacity requirements in a process order?
Please choose the correct answer.
- A. Phases
- B. Operations
- C. Resources
- D. Activities
Answer: A
NEW QUESTION # 48
Your project uses process orders for the production of liquid chemicals.
What can you define to ensure that production flow only happens in suitable physically connected tanks?
Note: There are 2 correct answers to this question.
- A. Resource hierarchy
- B. Resource network
- C. Resource selection
- D. Resource matrix
Answer: B,C
NEW QUESTION # 49
You have maintained the parameters for simple discontinuation in the material master of a component.
Which business process will be affected if the available stock is zero the discontinuation date is in the past?
- A. Back flushing
- B. Production order release
- C. Kanban
- D. Material requirements planning
Answer: D
NEW QUESTION # 50
To trigger a goods receipt posting, which Kanban status do you have to set?
Please choose the correct answer.
- A. Empty
- B. Full
- C. Wait
- D. In use
Answer: B
NEW QUESTION # 51
How would you define pegging in the context of Advanced Planning?
- A. An evaluation to identify overstock situations in the balance between the receipt the issue elements after the production planning run
- B. An evaluation to identify material or capacity shortages in the billofmaterial structure after the production planning run
- C. An evaluation that is ordered according to the network structure of all related products represents the coverage of issue elements with receipt elements stock
- D. An evaluation that is ordered according to the billofmaterial structure of all related products represents the relationship between the receipt the issue elements
Answer: D
NEW QUESTION # 52
In documentation for MRP in Advanced Planning you read that new orders are created through infinite planning.
What does this mean for the capacity requirements of a new order?
- A. MRP assigns the capacity requirements automatically after the last scheduled operation for each work center.
- B. MRP assigns the capacity requirements automatically to work centers with the earliest available capacity.
- C. MRP creates the capacity requirements without considering existing load on the work centers.
- D. MRP creates the capacity requirements at the earliest possible time.
Answer: A
NEW QUESTION # 53
Which business processes are affected by settings in the order type dependent parameters?
Note: There are 2 correct answers to this question.
- A. Define integration with cost accounting.
- B. Schedule production orders.
- C. Check material availability.
- D. Select master data.
Answer: A,D
NEW QUESTION # 54
What are the possible results of a production planning run in Advanced Planning (PP/DS)?
Note: There are 2 correct answers to this question.
- A. Production order
- B. Purchase order
- C. Scheduling agreement schedule line
- D. Planned order
Answer: C,D
NEW QUESTION # 55
Which planning strategies can you use in the capacity scheduling table?
Note: There are 2 correct answers to this question.
- A. Planning mode > Bucket
- B. Planning mode > Order priority
- C. Scheduling control > Close gap
- D. Scheduling control > Find slot
Answer: A,D
NEW QUESTION # 56
What could be the reason for multiple commitments where several operations have the same scheduled dates on a work center after dispatching?
Note: There are 2 correct answers to this question.
- A. The Change Planning Direction indicator is set in the strategy profile.
- B. The Finite Scheduling indicator is NOT set in the strategy profile.
- C. The work center has several individual capacities.
- D. Alternative work centers are fully occupied.
Answer: B,C
NEW QUESTION # 57
Which time elements are part of a routing operation?
Note: There are 3 correct answers to this question.
- A. Wait time
- B. Processing time
- C. Pick time
- D. Setup time
- E. Float before production
Answer: A,B,D
NEW QUESTION # 58
You are creating a production order manually. What activities are involved in this process?
There are 3 correct answers to this question.
- A. Order type determination
- B. Planning selection
- C. Actual cost calculation
- D. Capacity requirements determination
- E. Master data selection
Answer: A,D,E
NEW QUESTION # 59
What is a work center hierarchy?
- A. A group of work centers in a parallel sequence that is used to split production quantities work on them in parallel
- B. A group of work centers in a production line being used in sequence for production
- C. A group of alternative work centers for production structured in hierarchy levels by priorities
- D. A group of alternative work centers providing a cumulative available capacity for production
Answer: D
NEW QUESTION # 60
What happens when you set up detailed scheduling with the finite scheduling mode Insert Operation?
Note: There are 2 correct answers to this question.
- A. Sequencing on multiactivity resources is automatically updated.
- B. Scheduling of an operation takes place as close as possible to the desired date.
- C. Changes are automatically implemented in the complete collective order.
- D. Neighboring operations can be moved in both directions in order to create a slot.
Answer: B,C
NEW QUESTION # 61
......
Q&As with Explanations Verified & Correct Answers: https://practicetorrent.exam4pdf.com/C_TS422_2601-dumps-torrent.html

